Measure V

City of Dos Palos Measure V Update

Focus:

  1. Downtown Sidewalk Project to demonstrate Measure V
  2. Highest Traffic and Worst Quality Streets (high community use/near schools).
  3. Highest Traffic and Worst Quality
  4. Other Poor Quality
  5. Other Poor Quality

Strategies:

  1. Reduce Expenses:
    Bundle projects whenever possible, main street plus nearby feeders into one project. Saves staging, labor, and equipment costs.

  1. Increase Funding,
    Seek matching grants (bike path where applicable), and SB-I.
    Utility Funds, PG&E, telephone, cable, water, sewer, storm. Apply Center & Blossom Projects for Regional Funding

  1. Schedule up front: Bond or borrow first 3 to 5 years worth, at no or low interest, repay from Revenue Stream.
    Begin Underground Work ASAP to make surface shovel ready. Focus on Top Three Projects Simultaneously-Now.
    Stick to the plan, avoid changing priorities until project is completed.


Priority:

 1. Bank & Bubbles Downtown Sidewalk Project  $ 82,200
 2. Center Avenue North Area Project  $ 936,000
 3. East Blossom Street Area Project  $ 2,488,310
 4. Center Avenue South Area Project  $ 360,000
 5. Frank Avenue/Elementary Area Project  $ 320,000
 6. Downtown Sidewalks  $ 2,007,480
 7. Almond Avenue at Cemetery  $ 380,000
 8. Virginia Avenue  $ 390,000
9. Marks Subdivision  $ 370,000
10. Marguerite Street  $ 500,000
 Total Estimate of First Ten Projects as of 10-17-17   $ 7,854,310